The City Of Lewiston

Go To Search
Idaho's Only Seaport
Idaho Street ADA Ramps
As with all construction, unforeseen conditions could alter our well-intended notification plan and the construction schedule. If that happens, we ask for your cooperation and patience. We understand this will be an inconvenience for all of us and will do what we can to lessen the inconvenience.
Project Complete!
This project was finalized this summer with a total cost of $235,825.28.  Funding was a partnership of City funds (20%) matched to Federal Transit Authority funds (80%).  City funding was a mix of property tax, sidewalk fee-in-lieu of, and staff inkind services. 

Update 2/24/2014:
Project basically complete.  Only a few small items remain.

Update 9/17/2013:
Construction started on September 3 with ramp installation at the intersections of Delsol & G, Lincoln & G, Jefferson & F, 19th & Idaho, and 17th & Idaho.  Work will then continue west on Idaho Street.

Construction photos:
P9163271.jpg

P9123261.jpg

P9163283.jpg

Update 7/22/2013:
Construction bids opened on 7/15/2013 and A&R Construction was the lowest, responsible bidder.  The request to award a contract to A&R in the amount of $259,165.77 will be presented to City Council for approval at tonight's meeting

Funding for this project comes from the Federal Transit Administration (80%) and the match of 80% from City funds, which is a combination of property tax funds and FILO (fee-in-lieu of constructing sidewalk) funds.

Update 6/28/2013:
Project is out for bid and informational plans and specifications are available on the City Website under Bid Opportunities.

General Description

The City’s Transportation Advisory Committee worked with communty stakeholders to determine which streets or neighborhoods had the highest need for ADA improvements.  A list of project areas were developed and evaluated for greatest need and highest existing pedestrain volume.  From this list, Idaho Street was selected as the highest priority.  This project was developed to provide improved sidewalk access to all pedestrians along the corridor in accordance with the ADA mandate for public streets. 

This project also provides improved access to the City’s transit system.  In order to leverage the limited local funds available, the City will be using Federal Transit 80/20 matching funds for design and construction.  Once this project area was developed, it was identified to have a significant amount of overlap with the FEMA I Stormwater Project Area.  It was determined that the Accessible Ramp project should be coordinated with the FEMA stormwater project in order to reduce construction costs and the impact to the neighborhood.  The project was expanded to include an additional 10 ramps within the FEMA I Stormwater Project area.  A total of 41 new ramps will be constructed. 


Project Timeframe

  • Environmental Review/Approval Spring 2013
  • Design Winter/Spring 2013
  • Bidding June-July 2013
  • Bids Open July 10, 2013
  • Construction Summer 2013



 ADA Ramp and Catch Basin
                   

Project Manager
Shawn Stubbers, PE
Development Review/GIS Manager
208-790-8812


215 D Street
P O Box 617
Lewiston, ID  83501

                   
Public Works Department telephone:
208-746-1316

********************************
   Map of Project Area


Title VI and the Americans with Disabilities Act  |  Non-discrimination