2014 Street Preservation Work
Contact
Keith Bingman
Street Maintenance Manager

P.O. Box 617
Lewiston, ID  83501-1930

Ph: (208)746-2623
Public Works Main Phone 208-746-1316

As with all construction, unforeseen conditions could alter our well-intended notification plan and the construction schedule. If that happens, we ask for your cooperation and patience. We understand this will be an inconvenience for all of us and will do what we can to lessen the inconvenience.
______________
Update 8/18/14:
All contracted major street preservation work has been completed.  Thank you for your patience and cooperation.


Update 7/29/14:
2014 Residential Overlay Schedule as of 7/29/14
2014 Seal Coat Schedule as of 7/29/14

Update 7/23/14:
2014 Residential Overlay Schedule as of 7/23/14
2014 Seal Coat Schedule as of 7/23/14
2014 Slurry Seal Schedule as of 7/23/14

Update 7/18/14:
2014 Residential Overlay Schedule as of 7/18/14
2014 Seal Coat Schedule as of 7/18/14

Update 7/17/2014:
2014 Seal Coat Schedule as of 7/17/14
2014 Slurry Seal Schedule as of 7/17/14

Update 7/14/2014:
2014 Seal Coat Schedule as of 7/14/14

Update 7/11/14:
2014 Residential Cold Mix Overlay as of 7/10/14

Update 7/2/14:
2014 Residential Cold Mix Overlay as of 7/2/14
Map of the streets to received cold mix overlay

Update 6/30/14:
Project maps and schedules are posted!
Schedules:
2014 Residential Overlay as of 6-18-14
2014 Slurry Seals as of 6-18-14 
(schedule to be determined)
2014 Seal Coats as of 6-30-14

Maps - see at a glance if the street you are interested in is on this year's schedule:
Streets to be slurry sealed
Streets to be seal coated



2014 Street Preservation Projects Awarded
On May 12, 2014, the City Council awarded the 2014 Street Preservation projects.  One project consisting of seal coat work that includes seal coats, fog seals, quality patching, and base material and excavation to several streets was awarded to Herco, Inc. in the amount of $355,320.85.

A second contract in the amount of  $128,622.10 was awarded to Intermountain Slurry Seal, Inc. to slurry seal various streets throughout the city.

A map and schedule of streets will be posted soon.   Work is anticipated to occur in mid-June thru the end of July.  If you have any questions regarding any street work, please contact: