| Objective: Improve and upgrade the quality of City Roads |
| Action Steps |
Responsibility |
Completion |
| Implementation: 1. Adopt a Transportation Plan. |
| Done |
Van Stone |
Done |
| Implementation: 2. The Comprehensive Street Maintenance and Improvement Program is funded annually. |
2a. $817,460 is included in the FY '99 budget to accomplish the following: *Hot mix
overlay .89 miles of Thain Road *Chip seal 9.98 miles of City streets *Cold mix overlay 7.1 miles of residential street.
2b. Program funded in FY '99 budget. |
Manager / Council |
Annual Objective |
2c. Identify and apply for grant dollars to improve City streets. *Working to have State reconstruct Snake River Ave. *Pursuing retention of Bryden Canyon Road demonstration funds. |
Van Stone |
DONE for FY'98 Annual Objective. |
| *Awarded Southway bike and pedestrian path grant which will secure r-o-w for widening Southway ($490,000) and construct pathway. |
|
FY2001 |
| Implementation: 3. Improve the traffic safety on major streets. |
3a. Apply for a STEP Grant for traffic enforecement. *Two grants funded: radar speed trailer ($10,000); and overtime dollars for enforcement ($20,000) |
Baldwin |
DONE |
3b. Reconstruct / resurface roads to enhance traffic safety.
|
Van Stone |
DONE for FY'98 Annual Obj. |
3c. Safety deficiencies analyzed and identified in the Transp. Plan with the CIP identifying safety improvements.
|
Van Stone |
DONE for FY'98 Annual Obj. |
| Implementation: 4. Budget and construct Bryden Canyon Road. |
4a. Construction is underway
|
Van Stone |
01/99 |
| Implementation: 5. Promote use of indirect access to major streets. |
5a. An access policy is adopted as part of the Development Manual for all new construction
|
Van Stone |
DONE |
| Implementation: 6. Pursue State maintenance of East Main. |
6a. Public Works Admin. recommends hold until Bryden Canyon Rd. complete and decision made on Snake River Ave.
|
Van Stone |
When Successful |
| Objective: Promote City Beautification |
| Action Steps |
Responsibility |
Completion |
| Implementation: 1. Conduct valley-wide clean-up effort. |
1a.The City provides support for the following clean-up programs: *Adopt-A-Street *Boy Scouts litter pick-up (quarterly *LCSC Sr. Project litter clean-up |
Van Stone |
Annual Objective |
| 1b.Beautification Project underway which includes cleanup committee. Beautification Cmte: 1st Mtg: 12/03/98 --1st Mtg. of Beaty Lewiston Campaign: 12/08/98. |
Van Stone |
DONE |
| Implementation: 2. Implement a curbside recycling program. |
| 2a.Participation level in voluntary program is currently at 56%. Developing publicity campaign outlining benefits & ease of participation. |
Van Stone |
DONE |
| Implementation: 3. Promote street trees and landscaping. |
| 3a.Urban Forestry Mgmt. Plan outlines goals and strategies to achieve a healthy urban forest. Tree City - 10yrs. |
Van Stone |
DONE |
| 3b.Urban Forester plants 150 trees funded by donations and grants. |
Bowman |
DONE |
| 3c.Forester developing Normal Hill tree planting plan and Snake River Avenue Arboretum. |
Bowman |
DONE |
| Implementation: 4. Promote good public and private property maintenance as well as aggressive weed control. |
| 4a.Compaint follow-up, field demonstrations, public education and enforecement promote property maint. |
Bushfield |
DONE |
| Objective: Upgrade Police, Fire and Emergency Medical Services. |
| Action Steps |
Responsibility |
Completion |
| Implementation: 1. Enhanced 9-1-1 (System Upgrade) service is in place. |
| 1a.The rural addressing project in Nez Perce County is complete. Approved by electorate. Working toward implementation. |
Baldwin |
9/99 |
| Implementation: 2. Expanded Comm. Center provides opportunities for contracts with fellow valley agencies eliminating duplication. |
| 2a.Berry Architects of Eugene, OR is under contract for site selection and design. Funded in FY'99 Budget. |
Baldwin |
7/99 |
| Implementation: 3. Computerize access of fire and EMS response records. |
| 3a.Examine and implement computerization following E911 approval. |
Baldwin Tomberg |
Unknown |