June 20, 2023 | Restoration Project is 65% Complete

The on-site preparation work for the city's high reservoir wrapped up this month, following the completion of repairs to the exposed wall. The Liner materials arrived on June 16th, and crews will begin the installation process this week. 

The floating lid will be the next phase in the repair process, and that is expected to arrive the first week of July. 

The project remains on schedule at 65% complete. 

Irrigation restrictions remain in place. More information about restrictions can be found at https://www.cityoflewiston.org/752/Irrigation-Restrictions

Show All Answers

1. January 18, 2023 | Rupture Occurred
2. January 19, 2023 | Council Approves Resolution for Emergency Spending
3. January 25, 2023 | Reservoir Drained and Isolated from System
4. January 26, 2023 | Boil Water Order Lifted
5. January 23, 2023 | Council Issues a Continuance of Local Disaster Emergency
6. February 7, 2023 | Mayor Issues Order Terminating Local Disaster Emergency
7. February 23, 2023 | Technical Update Provided to Staff
8. March 27, 2023 | Council Approved Recommendation to Reuse the High Reservoir
9. April 17, 2023 | Discovery that First Plan was No Longer Viable
10. May 2, 2023 | Irrigation Restrictions Begin for Affected Water Customers
11. May 3, 2023 | Council Amends Emergency Expenditures Resolution
12. May 4, 2023 | Council Approves Second Proposed Plan and Contractor Moves Forward
13. May 12, 2023 | Demolition Begins
14. May 19, 2023 | Demolition is Complete
15. June 5, 2023 | Working with the DEQ
16. June 20, 2023 | Restoration Project is 65% Complete
17. July 7, 2023 | High Reservoir Liner Installed
18. July 31, 2023 | Irrigation Restrictions Lifted